Industries We Service

Coenen Mechanical was responsible for installation of a 300 HP/100 psi boiler system including the boiler, deaerator, skid mounted feed pump, steam/condensate/feedwater lines, and water make-up system. The system was installed and integrated into the plant’s manufacturing line.<p>As general contractor on this project, Coenen was responsible for layout and installation of equipment, procurement of piping, manual valves, and miscellaneous equipment, fabrication of piping, installation, start-up and commissioning.